Northpoint Data Center Power

ELECTRICAL DATA CENTER 2025
CLIENT
Northpoint Digital Infrastructure
LOCATION
Ashburn, VA
SIZE
40 MW / 310,000 sq ft
COMPLETION
Q3 2025

01Overview

CMS LTD was engaged to design the primary and redundant electrical distribution for a new 40MW data center campus, coordinating power delivery from utility interconnection through to rack-level distribution across four data halls.

02Scope of work

The team designed 2N redundant switchgear and UPS topology, medium-voltage distribution to each data hall, standby generator paralleling, and grounding/bonding systems sized for the facility's fault-current profile. Electrical design was coordinated continuously with mechanical cooling loads in a shared BIM model.

03Approach

Given the utility's multi-year interconnection queue, CMS LTD phased the electrical design to allow partial energization of the first two data halls ahead of full campus completion — sequencing switchgear procurement and commissioning around the utility's connection milestones rather than a single fixed completion date.